|
AECbytes "Building the Future"
Article (August 31, 2006)
2006 2nd Annual BIM Awards, Part 2
Last month, I published Part
1 of the article on the second annual
BIM Awards that were presented at the AIA
TAP conference in June. It described
the award winning projects in three of the
six submission categories: Creating Stellar
Architecture Using BIM (awarded to M. A.
Mortenson Company for the Denver Art Museum
Expansion project); Design/Delivery Process
Innovation Using BIM (awarded to GHAFARI
Associates for the Flint Global V6 Engine
Plant Expansion project), and Inspirational
Pilot Projects Demonstrating New Ways Forward
(awarded to Kirksey for the Satterfield
& Pontikes Corporate Headquarters project).
This AECbytes "Building the Future"
article discusses the award winning projects
in the remaining three categories of this
year's BIM Awards: Analysis or Simulation;
Jury's Choice; and Academic Program or Curriculum.
Category: Analysis or Simulation
Two firms received the BIM Award for this
category: Leo A Daly for the Georgia State
University Library project in Atlanta, and
Group Goetz Architects/Ehrenkrantz Eckstut
& Kuhn Architects for the Herbert C.
Hoover Building in Washington D.C. The common
thread running across both these projects
was the advanced use of the BIM model for
evaluating different aspects of the building's
performance.
Let's look at the Georgia State University
Library project first. This transformation
of a library building was part of the phased
redevelopment of the larger campus block
that the library was part of. The architects
were first retained to renovate the main
University Library building, including a
three-level enclosed bridge crossing over
to an adjacent library extension building
(see Figure 1). They were then asked to
also produce conceptual design studies and
phasing/constructability/cost proposals
for two new replacement buildings near the
library as well as the re-design of a series
of exterior landscaped plazas on various
levels interconnecting these buildings,
and relate these design studies to improved
site circulation to the library. The key
challenges were a very tight urban site
located at the heart of the campus with
multiple physical constraints on the design
and construction process; coordinating this
project along with other major campus redefinition
projects taking place simultaneously so
that their implementation would allow the
university to continue its daily activities
and functions; and controlling construction
costs while evaluating and implementing
multiple design options. With the client
anxious to meet the immediate needs of the
library renovation/expansion as well as
to receive guidance on related renovation/redesign
of the exterior plazas, the design team
was quickly expanded to include a local
contractor acting as CM for comparative
cost/phasing analyses and a local structural
engineer for analyses of the expanded library
bridge.
Figure 1. A section through the
Revit model of the Georgia State University
Library project, showing the main University
Library building, the three-level enclosed
bridge crossing over to the adjacent library
extension building, and the plazas connecting
the library with two new buildings. (Courtesy:
Leo A Daly)
The design team utilized BIM from the inception
of the project to better meet its programmatic
complexities, phasing demands, fast-track
scheduling and other design challenges.
In fact, apart from three sketches, the
project was exclusively developed using
Autodesk Revit Building, with no supplemental
manual drafting. The structural design was
done with Revit Structure, while the MEP
engineer used AutoCAD and Trace 700 load
calculator. BIM was used for all the different
components of the project, starting from
the plaza studies and urban design, where
it was used for 3D studies of the experiential
connectivity of the various plaza levels
with the streetscape; integration of the
new library entrance with plaza site circulation;
analysis of the space-enclosing building
walls, both current and proposed, surrounding
the plaza levels; implication of the plaza
re-design on site circulation patterns;
sun studies to examine shade, shadow, and
sunlight penetration resulting from the
plaza and building modifications (see Figure
2); and phasing analyses and cost estimates
for the plaza re-designs by the contractor
(CM).
Figure 2. Sun studies of different
aspects of the design using the Revit model.
(Courtesy: Leo A Daly)
For the main library building, BIM was
used for elevation studies to determine
the best glazing options for visual connectivity
with the plaza; conceptual studies of various
connecting bridge designs, along with long-span
structural design options (see Figure 3);
advanced CPM planning of the library renovation,
the identification of major lead items (steel,
HVAC equipment and glazing options) and
the creation of five distinct design packages
for optimal constructability; and integrated
coordination of the library renovation phasing
with the designers, CM and client to meet
a highly aggressive construction schedule.
For the library bridge, engineering simulations
helped to determine that horizontal overhangs
were insufficient for shading on the southwest
façade, calling for the use of vertical
fins instead; in contrast, the north-east
façade was being shadowed by the
surrounding buildings and didn't need any
kind of shadowing devices, which were retained
for decorative purposes only.
Figure 3. The Revit platform being
used for both the architectural and structural
design of the library bridge. (Courtesy:
Leo A Daly)
Since the project team was distributed
across ten offices in four different cities,
interoperability was critical and was achieved
by the use of the same platform for architectural
and structural design, and by sharing the
model with the Construction Managerwho
was using ArchiCADthrough NavisWorks.
All the necessary Revit model attribute
data (e.g., floor areas, quantities, skin
takeoffs, etc.) were able to be extracted
and shared between the design team and the
CM, eliminating the need for manual quantity
takeoffs and rework. A shared electronic
project portal was set up where all the
data files were stored, and real-time inter-office
connectivity was achieved by using Riverbed
Steelhead Appliance data-caching technology,
which eliminated errors caused by working
from multiple data sets.
The second project that received the BIM
Award for the Analysis or Simulation Category
was the comprehensive modernization and
renovation of the famous Herbert C. Hoover
Building in Washington DC for the GSA (General
Services Administration). Originally constructed
in 1933, this historic National Landmark
buildingonce the largest in the world
with 1.8 million sq. ftis part of
an ensemble of buildings known as the Federal
Triangle and is considered the most significant
example of Beaux Arts architecture in the
world (see Figure 4). It currently houses
the headquarters for the Department of Commerce,
the White House Visitors Center, and the
National Aquarium. The modernization of
this building, scheduled in four phases
over the next 12 years, involves installing
new building systems, new life safety systems,
ADA accessibility, new utility connections,
significant security upgrades, new flexible
office space, new landscaping, and restoration
of the exterior façade. What made
the project especially challenging was to
install the new building systems in a structure
not originally designed to house them, and
to create new office space into four existing
floors with minimal ceiling heights, along
with new vertical circulation and egress.
Other key challenges were an irregular column
grid and infill levels whose floor elevations
are not aligned with the main building floor
level structure.
Figure 4. The Herbert C. Hoover
Building in Washington D.C, partially overlaid
by the BIM model that was developed for
the modernization project. (Courtesy: Group
Goetz Architects/Ehrenkrantz Eckstut &
Kuhn Architects)
The architectural team at Group Goetz Architects/Ehrenkrantz
Eckstut & Kuhn Architects strongly felt
from the beginning that BIM should be adopted
on this project to better understand the
complexity of the existing building and
determine how best to weave and surgically
insert new systems and other components
into the existing structure. It also believed
that using BIM would ultimately save significant
time, minimize potential field conflicts
and change orders, minimize costly exploratory
demolition, and provide valuable quantitative
information to all team members during the
long project schedule. The software solutions
adopted were Autodesk Architectural Desktop
for creating the BIM model and any related
CAD work, Autodesk VIZ for generating renderings
for communication with the clients, and
Microsoft Excel for processing information
retrieved from the BIM model.
While the project is still ongoing, the
benefits of using BIM have already been
realized in several specific areas. For
example, a courtyard of the original building
that housed a four story infill space within
an eight story light well was being redesigned
to reinstate the roof with a green roof
and a partial skylight to allow natural
light into the office floors, which required
relocating the existing HVAC systems to
lower levels with the courtyard. A detailed
BIM model was used to determine how to maximize
ceiling heights, introduce daylight, create
life safety egress, and distribute new air
to each of the floors and the adjacent White
House Visitor Center and Law Library, while
minimizing disruption to these adjacent
historic spaces (see Figure 5).
Figure 5. Using the BIM model to
redesign the interior courtyard. (Courtesy:
Group Goetz Architects/Ehrenkrantz Eckstut
& Kuhn Architects)
In another example involving doors and
windowsthe building has over 5000
exterior historic windows and over 10,000
historic doorsthe team modeled and
tagged each door and window within the building
model for future restoration or re-use where
possible, as well as to determine the best
blast protection method for each window
(see Figure 6).
Figure 6. Modeling and tagging
the windows in the building model to determine
different restoration or re-use options.
(Courtesy: Group Goetz Architects/Ehrenkrantz
Eckstut & Kuhn Architects)
The use of BIM was also invaluable for
the design team to quickly and efficiently
explore different options for accommodating
more office space in the building for a
larger number of occupants as well as increased
conference and amenity spaces. They used
the BIM model to create a matrix of area
objects that fit the six unique floor plan
varieties in the building, and tied each
of these back to a Master density and population
matrix that included circulation, shared
spaces, etc. By moving departments around
within this model, the matrix would report
which combination of adjacencies allowed
or did not allow the appropriate fit (see
Figure 7).
Figure 7. Exploring multiple office
options to accommodate the optimal fit of
density and population in the building.
(Courtesy: Group Goetz Architects/Ehrenkrantz
Eckstut & Kuhn Architects)
The use of BIM for design and analysis
in this project and the benefits that are
being realized makes a significant contribution
in highlighting that BIM is not just for
new buildings and new construction. Complex
existing renovation projects or historic
modernizations, as in this case, can also
make excellent candidates for using BIM
tools and technology.
Category: Jury's Choice
The award winning project in this category
was the Merck Research Laboratories building
in Boston, a twelve-story research laboratory
tower with six levels of below grade parking
located in the Longwood Medical Area of
Boston, a highly active educational, cultural
and historical environment. Kling was the
lead architect on this project, while Bovis
Lend Lease was the lead contractor. The
tight constraints of its downtown Boston
location dictated that a multitude of typically
discrete functions (research, administration,
conferencing, reception, dining, parking,
and utilities) be housed in a single building
(see Figures 8 and 9). This "vertical
campus" of high-technology spaces presented
an implicit challenge to the design team.
Other key design challenges were resolving
a normally introverted program in an open,
light-infused, "public" manner,
and the complex layering of system distribution
and public/private movement.
Accordingly to Kling, their BIM approach
to this project can be parsed into two levels:
Basic Documentation, a continuous process
whereby the "current" design solution
is described and maintained; and Advanced
Analysis, a periodic charrette approach
used for the most challenging design problems.
At the Basic Documentation level, MicroStation
Triforma was used to develop the BIM model,
including the entire structural system,
the architectural finishes, and the major
mechanical spaces (see Figure 8).
Figure 8. The multi-disciplinary
BIM model of the Merck Research Laboratories
building project. (Courtesy: Kling)
The use of a single software platform
within the multi-disciplinary team allowed
for the day-to-day referencing of models
between architects and engineers. The significant
scale of this project is reflected in the
fact that the "master" BIM model
referenced a total of 104 architectural,
structural and mechanical models. From the
master model, schematic-level plans, sections,
elevations and oblique orthographic drawings
were generated for the drawing sets. The
model was also used for visualization, though
full-building renderings and animations
often required the use of a simplified MicroStation
model optimized for 3D rendering (see Figure
9).
Figure 9. Photorealistic renderings
of the Merck Research Laboratories building
project, generated from the BIM model. The
corresponding views in the completed building
are also shown alongside. (Courtesy: Kling)
At the conclusion of the Design Development
phase, when the basic organizational schema
of the building had been coordinated, the
overall architectural plans and sections
were separated from the Building Information
Model, and became conventional, 2D architectural
documents. The focus of the BIM process
then turned to what Kling describes as the
Advanced Analysis level, dealing with the
development of the building's most complex
elements that required more intense analysis
and 3D visualization in order to bring them
to resolution. For example, the 290-seat
auditorium, which was the most spatially
complex challenge for this project, was
made possible by a BIM process that included
the architectural team, the engineering
team, and the millwork subcontractor. Its
geometry was optimized to accommodate sight
lines, acoustical criteria, lighting and
environmental control, and did not include
any parallel surfaces or horizontal lines,
but it was still fully veneered in wood,
defying the level/plumb/square logic of
standard wood construction (see Figure 10).
The milling subcontractor took the idealized
BIM model developed by the architectural
team and developed it further incorporating
site conditions and constructability issues.
In the process, several issues and conflicts
were resolved in the digital model that
would have become significant on-site construction
challenges had they remained undetected.
The BIM model was also used to fabricate
the ribs and panels at the millworker's
shop that were then erected on site. The
process was so accurate that no panels needed
to be modified or sent back to the shop.
Figure 10. The advanced use of
BIM in the design and construction of the
spatially complex auditorium. (Courtesy:
Kling)
Other examples of the use of BIM at the
Advanced Analysis level include the multi-disciplinary
design and coordination of complex components
of the building including the sloping entrance
canopy, the atrium framing system, and a
steel, glass and stone reception desk that
is cantilevered directly from the building
structure. For the mechanical systems design,
BIM models were constructed for the three
major mechanical areas, with piping being
modeled down to the 3" diameter level.
The atrium smoke evacuation system was coordinated
within the BIM model, and later analyzed
in a CFD (Computational Fluid Dynamics)
model; also, the air intakes, located at
the major façade, were coordinated
with the curtain wall in the BIM model.
In addition, BIM was used to resolve conflicts
between several drivers below-grade, including
parking ramps, major mechanical spaces,
suspended elevator shafts, the sloped auditorium
floor, and the building structure.
In addition to the BIM Award, the Merck
Research Laboratories building has also
won several design awards, including the
2004 AIA Local Chapter Gold Medal, the 2005
AIA State Chapter Citation of Merit, the
2005 AIA Local Chapter Award for Design,
and the 2005 AIA Regional Citation for Design
Excellence. It is heartening to see the
advanced use of technology in a project
also commended for design excellence, dispelling
any notions or concerns that the use of
BIM could negatively impact architectural
creativity and aesthetics.
Category: Academic Program or Curriculum
An Honorable Mention in this category was
awarded to UIC (University of Illinois,
Chicago) School of Architecture for their
project aimed at developing an understanding
of the current and future state of BIM and
its implications for education as well as
practice. A recently completed building,
the Elgin Fire Station #6 in the city of
Elgin, Illinois, that had been designed
using traditional CAD methods was completely
digitally recreated as a smart building
model using VectorWorks Software, donated
for the project by Nemetschek North America.
The academic team worked in collaboration
with FGM Architects, a large, local architecture/engineering
firm which was the architect of record for
the case study building. This firm shared
all the construction document information
which the academic team used to create the
BIM model of the building in all its complexity,
including architectural, structural, mechanical,
plumbing and electrical information (see
Figure 11). Each team member is acting as
a consultant on the overall building model.
When the project is completed, the core
team will present the model to the firm
to help them implement BIM technology firm-wide.
Figure 11. The multi-disciplinary
BIM model of the Elgin Fire Station, created
by the UIC School of Architecture team.
(Courtesy: UIC)
In the course of this project, the academic
team identified both the benefits as well
as challenges of BIM. It found that BIM
technology results in a better integrated
building, as it enables the initial design
concept to be expressed not only in the
architectural elements, but also in structural,
mechanical, and other disciplines. Since
all building systems can be designed concurrently
while utilizing BIM technology, the original
design intent is not sacrificed during the
construction document phase. BIM also enables
rapid visualization of design options without
much resource investment. One example of
this is the adjacency matrix tool in VectorWorks,
which can generate a variety of building
layouts based on program analysis and rank
them according to scores. On the downside,
the lack of BIM content from product manufacturers
means that all elements must be modeled
individually by the user which is very time-consuming.
Also, the technology allows for such precision
in the model that new attention must be
paid in allowing for tolerance in construction
and manufacturing of parts. While the process
of breaking the master model into separate
parts for each trade to work on has gone
fairly smoothly, difficulties have occurred
when breaking these discipline specific
models into smaller parts for multiple people
to work on at the same time. The team feels
that this could be a major hurdle to the
implementation of BIM technology on a large
scale.
In addition to the BIM application, one
of the primary project tools was the project
team website, which has facilitated file
sharing, discussion boards, access to all
team members' research, and a team calendar.
The academic team concludes that collaboration
has been the primary factor in the success
of this project, and that this will be the
key to the future success of BIM technology
and the primary component of the cultural
change taking place in architecture. The
team also recommends that academic curricula
should work on integrating building science,
structures, theory and design to produce
comprehensive building projects, and should
provide students the opportunity to build
projects at 1:1 scale so that students graduate
with the knowledge and skills to be "building
model operators," not draftsmen.
This wraps up the two-part series on the
second annual BIM Awards that were presented
at the AIA TAP conference in June. The annual
competition is a great way to track the
progress of BIM adoption, and 2007 should
see an even larger number of entries and
more advanced examples of BIM implementation.
Acknowledgements
I would like to thank all the winning firms
and schools cited here who allowed me to
use the material they had submitted for
the BIM Awards for the purpose of writing
this article.
About the Author
Lachmi Khemlani is founder and editor of
AECbytes. She has a Ph.D. in Architecture
from UC Berkeley, specializing in intelligent
building modeling, and consults
and writes on AEC technology. She can be
reached at lachmi@aecbytes.com.
If you found this article useful and
have not yet subscribed to AECbytes, please
consider doing so. Subscription
is free, and more subscribers will allow
this publication to provide more of such
content to you.
|