|
AECbytes "Building the Future"
Article (September 30, 2006)
Building Owners Driving BIM: The "Letterman
Digital Arts Center" Story
Mieczyslaw (Mitch) Boryslawski, Associate
AIA
Founder, View By View, Inc.
Our world has changed, our economy has
changed, and so has the design and construction
industry. It is going through an overhaul
never seen before by adapting smart parametric
digital technology that in the past was
used only by the automotive, shipbuilding,
and aircraft industries. Many of the lessons
and experiences learned in these industries
are being transferred to the more static
design and construction industry.
Building owners are pioneering this rediscovered
technology, commonly referred to as building
information modeling, or BIM. After all,
these owners are at the very core of the
design and construction industry and have
the most to gain. They have the power to
eliminate the unnecessary waste, in both
time and resources, and the associated cost
burden facing the AEC industry. Indeed,
the new client mandate is rapidly changing
this industry. My company, View By View,
had the opportunity to implement BIM on
the Letterman Digital Arts Center commissioned
by LucasFilm Ltd. in San Francisco, not
only for design resolution but also within
the construction process. This article captures
some of my insights and experiences working
on this project.
Overview of the Letterman Digital Arts
Center Project
The Letterman Digital Arts Center (LDAC)
is intended to be the world's premier digital
arts center, with cutting-edge special effects
production suites and video game development.
It is located on a 23-acre site in the Presidio
National Park, San Francisco, California,
of which 17 acres was returned to the park.
Designed like a campus to house 1,500 employees,
the LDAC comprises four buildings and a
theatre with a total area of 865,000 square
feet and an underground garage of 717,000
square feet, providing 1,500 parking spaces
with four levels underground. The structure
is a post-tensioned concrete frame with
steel framing on the top levels. Three buildings
are enclosed with external plaster stucco
walls and two buildings are clad with brick
panels (see Figure 1). The buildings have
a raised floor system, containing the MEP
system placed on the concrete floors, then
covered and sealed with metal floor panels.
The raised floor system is a fairly new
concept in the USA but very common in Europe.
Construction on the project started in January
2003 and was completed in June 2005. More
information on the Letterman Digital Arts
Center, including images of the finished
building, can be found here.
Figure 1. Computer generated renderings
of the LDAC. The top image shows the entire
campus, while the lower images show the
individual buildings.
The LDAC needed a staggering amount of
technology to simulate a "virtual movie
set," that would allow the employees
to share files simultaneously on the different
screens from different parts of the buildings.
Building A, shown in the lower right image
of Figure 1, has a 1200 square feet server
farm and an 800 square feet media production
suite. Some 600 miles of fiber-optic cable
runs between 3000 AMD processors, with 10
500 gigabytes ports supported by 100 terabytes
of storage. With the capacity for 14,000
processors, the center can move 1,000 terabytes
of data a day across the building's 10 gigabit
fiber network. Digital artists can feed
high-resolution footage directly to the
300 seat theater's large 49 foot by 21 foot
screen in a matter of seconds. New computer
infrastructure was specifically designed
for this project. The raised floors of the
building that accommodate the MEP system
were also designed to allow access to this
complex technology for future updates.
The BIM Process in the LDAC
View By View was selected to join the LDAC
project management team, representing the
owner and acting as a design and construction
coordinator, detecting interferences between
various disciplines and assisting in the
resolution of design issues. The adoption
of BIM technology for this project evolved
over time and intensified as the benefits
of creating a detailed, dimensionally accurate
3D product model became evident. BIM was
adopted in the post-design phaseafter
most of the design documentation on the
project had been completed in 2D. Initially,
a polygonal surface 3D model was created
to provide photorealistic views of the project
for the Presidio Trust and public viewing,
as shown in Figure 1. Polygonal surface
models are not intelligent models as they
contain only 3D geometry and surfaces with
materials applied to them. The natural progression
was to take the process further and create
a 3D model that could be useful for the
life of the project, containing accurate
information on the building product systems
and also creating an "as built"
3D intelligent model. To accomplish this
task, View By View recreated the 3D model
by implementing BIM technology, which is
shown in Figure 2.
Figure 2. The building information
model (BIM) of the Letterman Digital Arts
Center.
One of the most important requirements
for effective collaboration using BIM is
to ensure that all team members are involved
in creating the core building information
model. Starting with the LDAC project management
team, architects, structural and mechanical-electrical-plumbing
(MEP) engineers, contractors and fabricators
actively followed and provided input into
the BIM process. It started with the creation
of the 3D structural model, followed by
the architectural components, and later,
as they became available, with all of the
MEP elements. The other critical issue was
to make sure that the latest information
flowed through the process within the core
building information model. A read-only
server, dedicated to the BIM process, was
installed in the project site office (see
Figure 3). Once all the 3D data was available,
it was consolidated into a single building
information model, using a unique highly
compressed technology developed by NavisWorks
Ltd. This technology and the ability to
assemble 3D large and complex models from
almost any CAD application on the market
today makes NavisWorks a must in the project
management tool box.

Figure 3. The Citrix read-only
server dedicated to holding the single building
information model.
The building information model was updated
on a weekly basis and posted to the server.
The management of the digital assets was
the sole responsibility of View By View.
When a revised model was made available
for publishing to the server, the previous
model was automatically updated. Any older
models that were downloaded to the local
PC were no longer activated since they were
timed on a weekly basis. This process worked
extremely well since all the team members
had access to the most current information,
eliminating potential communication problems
that could arise by referencing the out
of date model. It also minimized the request
for information (RFI) process, which requires
considerable resources in typical construction.
However, one challenge that we did face
in maintaining the integrity of the BIM
was staying ahead of the many changes or
omissions that occurred during design and
construction, and to ensure that we always
were delivering up to date "as-built"
data to the client. It was not uncommon
for the designers or the contractor to make
changes on the job site without reflecting
those changes on their drawings.
Since the design documentation for the
project had been done in 2D, there were
some instances where using out-of-date drawings
caused problems, such as the one illustrated
in Figure 4, where a steel truss was penetrating
the aluminum curtain wall. The problem was
discovered during a visual conflict check
of the building information model and was
reported to the LDAC management team. The
steel frame had already been manufactured
by the steel fabricator but had not yet
been delivered to the site. It was modified
in the shop after the problem was detected,
thereby minimizing the costs of a possible
change order. Another coordination problem
that was detected and resolved using the
building information model is shown in Figure
5.
Figure 4.
The two left images are renderings from
the building information model, showing
the conflict between the steel truss and
the aluminum curtain wall. The photograph
on the right was taken from below after
the problem was corrected and the steel
roof properly installed.
Figure 5. Example of a coordination
problem in the elevators machine rooms that
was detected and resolved using the building
information model.
During this BIM process, which paralleled
the actual construction of the project,
many other discrepancies and unresolved
design issues were found between the structural,
architectural and mechanical systems. These
were pointed out to the team members during
the weekly variance meetings (shown in Figure
6), enabling corrections to occur often
days before the actual construction of the
relevant elements. By incorporating the
contractor's shop drawings as another layer
in this process, additional errors were
found which, if left unchecked, would have
resulted in considerable costs to the contractor
and delays in the construction schedule.
An additional advantage was that by working
on the site full time, we conducted regular
site walks, recorded everything digitally,
and by comparing the digital photographs
with the 3D model, we were able to identify
further discrepancies between what was being
built and what was intended. Having already
constructed the building "virtually,"
deviations from the design became quickly
evident to us.

Figure 6.
The weekly variance meetings held for the
LDAC project, in which many potential design
problems were detected and resolved using
BIM.
Unfortunately, there were a few problems
that were undiscovered during the visual
scanning of the building information model
and had to be later corrected on the site.
This was partially due to the fact that
the BIM process started after the design
documents were 60% completed. Ideally, if
the process had begun during the early design
stage, more problems would have been avoided,
including the complex MEP design issues.
Of course, this process is not infallible,
but the earlier the process is started and
the more experience one has in this field,
the better probability there is of identifying
and resolving potentially expensive problems.
In order to assess the benefits of the
BIM process on the project, we undertook
some design coordination variance cost studies.
An example is illustrated in Figure 7, which
shows the cost implication of incorrectly
cast concrete beams. These beams, occurring
in the central stairs of one of the buildings,
should have been downturned instead of upturned
as there are no raised floors in this part
of the building. Using BIM, the error was
discovered after the formwork was completed
(in the orange zone in the graph) but before
the concrete was poured (in the red zone),
when the correction would have been a lot
more expensive.
Figure 7. A graph showing the cost
implication of incorrectly cast concrete
beams. Using BIM, the problem was discovered
in the orange zone, when the formwork was
already in place, still averting costly
corrections had it been found in the red
zone, after the concrete had been poured.
On the LDAC project, we found that despite
the efficiency of BIM, there still exists
the possibility of human error, as illustrated
in Figure 8. During one of the daily rounds
of onsite photography, we recognized a critical
error shown in the positioning of concrete
formwork, an error that was quickly confirmed
by referencing the BIM. This error occurred
when the formwork layout person measured
to the edge of concrete slab from a column
that was off the standard grid. Pouring
more concrete (shown in gray in the photo
on the left) in this complex post-tension
slab construction would have had a serious
consequence not only for the contractor
but also for the entire project, as there
were three more floors to be built above
this floor. Because of our familiarity with
the virtual model and having experienced
the building spaces before construction,
we were immediately able to identify the
problem and alerted the LDAC management
team. The problem was solved just as the
concrete was being poured, saving what would
have most definitely been a major expense
to rectify later.
Figure 8. Even the use of BIM is
not fool-proof. The gray transparent slab
shown in the photo on the left is the graphic
representation of the extra slab that would
have been poured if not caught by visual
inspection literally minutes before the
pour was to occur.
Pushing the Use of BIM Even Further
In addition to identifying and resolving
coordination problems, the building information
model was also gainfully used in other ways.
Laser measuring and pointing devices guided
by specialized software using the building
information model data were used to check
for the accurate positioning of pipes in
the data center. Another critical use of
the building information model was to simulate
an emergency situation. For example, since
we had a 3D model of all the complex mechanical
piping located in the parking levels, we
were able to simulate the height clearance
required for the Presidio fire department
fleet of fire fighting trucks to access
the underground parking in case of an emergency
(see Figure 9). The NavisWorks clash detector
module was used for this clearance check.
We have also discussed the possibility of
installing smart dust chips technology in
critical areas of the MEP building systems,
such as fire sprinklers main valves. Once
the smart chip detects an emergency situation,
the building information model will activate
the area of concern and simulate the necessary
steps to be taken with the use of 3D avatars,
such as those using in the online gaming
industry.
Figure 9. Using the BIM model to
check for accessibility of fire trucks in
the underground parking levels.
4D or construction time-based sequencing
simulation was also used on this project.
248 activities were identified, on the basis
of which the LDAC cost estimators created
a construction time-based schedule. Once
the tasks and the area of simulation were
identified, a simplified 3D model derived
from the BIM model was imported into the
4D application. Links were created between
the 3D objects in the model and the schedule.
The end result was a time-based animation,
which could automatically update with any
change of time for a task. One important
lesson we learned from this process was
that a tremendous amount of time can be
saved if the naming convention for both
objects (within the 3D model) and tasks
(within the scheduling software) can be
agreed to in advance. This will allow for
much more rapid linking between the two
technologies, and much less chance of omitting
the necessary elements of any construction
sequence.
Moving forward, we see a number of exciting
opportunities on the horizon. Of immediate
interest to the LDAC team is the leveraging
of the building information model by facility
managers for long-term operational efficiency
of the Center. For years, facility management
has been based primarily on text and line
data linked by specialized database software.
What we are proposing is to link the 3D
parametric-based objects to the same external
data instead of 2D line drawings. It will
allow facility managers to explore critical
building systems more thoroughly and accurately
within the 3D environment.
Conclusions
Despite numerous design layout changes
that were required by LucasFilm Ltd. due
to company restructuring, the LDAC project
was completed on time and below the estimated
budget. There was no finger pointing during
and after completion of the project as most
of the problems were solved before construction.
Through careful site coordination using
BIM, over two hundred design and construction
conflicts were identified, most of which
were corrected before construction, resulting
in an estimated savings of over $10 million
on this $350 million project.
While our experience with this new technology
was exciting and rewarding and at times
frustrating, our experience with the LDAC
project confirms that technology alone is
not the ultimate solution. Developing and
managing the partnerships between all concerned
parties involved in the design-build process,
particularly with owners, designers, builders
and fabricators was unquestionably a critical
component to its successful implementation.
The Letterman Digital Arts Center (LDAC)
project demonstrates that the critical decline
in productivity facing the construction
industry in this country can be overcome
by forward thinking owners and the project
management team implementing a construction
management process centered around the creation
of a smart virtual building information
model. The real value of using the BIM process
lies in the sharing and integration of information
with multiple end-users, designers, contractors,
and suppliers through the life cycle of
the project.
It must also be emphasized that the success
of the LDAC project can be attributed in
large part to significant commitment made
by the owner towards implementing BIM technology.
Funds were allocated to the general contractor
for the purchase of software applications,
training and creating the 3D MEP product
data for those sub contractors that were
not trained in 3D technology. Integrating
a smart virtual construction model into
the construction management process takes
intelligence, courage, vision, enthusiasm
and most of all, an intimate understanding
of the design and building construction
processes themselves. What the LDAC project
demonstrates is that far-sighted building
owners who invest in the construction of
smart building information models can realize
significant costs savings, not only in the
design and construction process but also
in the maintenance and operation of the
life cycle of the building.
About the Author
Mieczyslaw (Mitch) Boryslawski is the Founder
of View By View, Inc., which he propelled
from its initial role as an architectural
visualization service bureau in 1990 to
its current status as one of the first companies
to have taken BIM through the entire construction
process. Mitch was born in Poland, and educated
in Europe, South Africa and the USA in architecture
and construction project management. He
is a frequent speaker on digital architecture
and BIM, has been involved in international
architectural competitions for the last
30 years, and has won several awards including
the 2005 "Digie" Award for the
Best Use of Automation-Architectural Design.
His 3D digital work on the "Greening
of the White House" is permanently
on display at the Old Executive Office Building,
The White House, Washington D.C. Together
with CREST, he also produced the "Greening
of the White House" interactive CD-ROM,
an environmental project funded by the department
of Energy and published by the American
Institute of Architects, Washington DC.
The CD-ROM was demonstrated by the then
First Lady Mrs. Hillary R. Clinton and premiered
on the "Good Morning America"
TV show. He can be reached at Mitch@viewbyview.com.
If you found this article useful and
have not yet subscribed to AECbytes, please
consider doing so. Subscription
is free, and more subscribers will allow
this publication to provide more of such
content to you.
|